title: How Long Does Custom Automation Take? Plan for a Year
description: Custom automation takes about a year from PO to production. See where the time goes and how to plan capex and payback around it.
image: https://www.pezosolutions.com/hubfs/image-32cf2c86-a1b3-4472-94ed-c70747324b7e.png
---

[Skip to content](https://www.pezosolutions.com/the-cleanroom-ledger/how-long-does-custom-automation-take#main-content)

[![Middle Blue Pezo Solution Logo with White Background PNG](https://www.pezosolutions.com/hs-fs/hubfs/accent1.png?width=1200&height=900&name=accent1.png)Homepage](https://www.pezosolutions.com/)

- [Capabilities](https://www.pezosolutions.com/the-cleanroom-ledger/how-long-does-custom-automation-take#capabilities)
  
    - [R&D + Product Design](https://www.pezosolutions.com/rd-product-design)
    - [Manufacturing Process Design](https://www.pezosolutions.com/manufacturing-process-design)
    - [Precision Machining](https://www.pezosolutions.com/precision-machining)
    - [Automation & Machine Integration](https://www.pezosolutions.com/automation-machine-integration)
- [Cleanroom Workstations](https://www.pezosolutions.com/elevt-workstations)
- [GS 5T](https://www.pezosolutions.com/gs-5t-bench-top-catheter-overmolding-press)
- [About](https://www.pezosolutions.com/about)
- [Blog](https://www.pezosolutions.com/the-cleanroom-ledger)

[Get In Touch](https://www.pezosolutions.com/get-in-touch)

- [Capabilities](https://www.pezosolutions.com/the-cleanroom-ledger/how-long-does-custom-automation-take#capabilities)
  
    - [R&D + Product Design](https://www.pezosolutions.com/rd-product-design)
    - [Manufacturing Process Design](https://www.pezosolutions.com/manufacturing-process-design)
    - [Precision Machining](https://www.pezosolutions.com/precision-machining)
    - [Automation & Machine Integration](https://www.pezosolutions.com/automation-machine-integration)
- [Cleanroom Workstations](https://www.pezosolutions.com/elevt-workstations)
- [GS 5T](https://www.pezosolutions.com/gs-5t-bench-top-catheter-overmolding-press)
- [About](https://www.pezosolutions.com/about)
- [Blog](https://www.pezosolutions.com/the-cleanroom-ledger)

[Get In Touch](https://www.pezosolutions.com/get-in-touch)

![Shows a timeline with milestone discs, an hourglass, gears and a small machine.](https://www.pezosolutions.com/hs-fs/hubfs/image-32cf2c86-a1b3-4472-94ed-c70747324b7e.png?width=1000&height=558&name=image-32cf2c86-a1b3-4472-94ed-c70747324b7e.png)

Automation Capex Planning Medical Device Manufacturing

# How Long Does Custom Automation Take? Plan for a Year

![Mark Kiviahde](https://app.hubspot.com/settings/avatar/a1b2585cd0202205cce0c96dfe09784b)

 Mark Kiviahde

November 18, 2026

**The short answer:** Plan on about a year. A custom machine quoted at 26 weeks usually shows up closer to 40 weeks. Then it needs a few more weeks of debugging before it makes good parts. Add your capex approval on the front end, and the payback clock starts later than most people expect.

That is not a sales line. It comes from Andy Larson, founder of Custom Automation Inc., now part of Pezo. Andy has spent nearly 40 years designing one-of-a-kind automation machines. In his words, "It's basically going to be a year before it really starts making product."

Here is where that year goes, and how to plan around it.

#### Where the time goes

| Stage | Typical time | What happens |
| --- | --- | --- |
| Scoping | 2 to 8 weeks | Site visit, part review, rough machine concept, budget quote |
| Capex approval | Depends on your budget cycle | Funding gets approved, often tied to the calendar year |
| Design and build | 26 weeks quoted, often about 40 actual | Mechanical design, controls, fabrication, assembly, programming |
| Install and debug | Several weeks | Machine goes in, gets tuned to real parts, operators get trained |
| Ramp to full output | Ongoing | First good parts ship, payback starts |

#### Why a 26-week quote turns into 40

Custom automation is one-of-a-kind work. Nobody has built your exact machine before. A few things stretch the schedule almost every time.

- **Programming comes last.** Controls work can't finish until the mechanical build is done. If the build runs late, the programmer gets squeezed.
- **Real parts behave differently.** A person can adjust to a part that is a little off. A machine can't, unless it has vision. Debugging often means finding variation in incoming parts that nobody knew was there.
- **The design can't change.** In medical devices, a validated part is locked. The machine has to work around the part as it is, even when a small change would make automation easier.

None of this means something went wrong. It means you should plan for it from day one.

#### How capex timing affects your schedule

Most automation projects at this level cost $500,000 or more. That means a capital budget and sign-off from a director or VP. Budgets are usually set once a year.

We often see customers ask to split billing across December and the new year. That is normal. But if you miss the budget window, your project can slide a full year before design even starts.

#### What this means for payback

Most manufacturers want automation to pay for itself in about two years through labor savings. That two-year clock starts when the machine makes good product. It does not start when you sign the PO.

So if you need savings by a certain date, count back at least a year for the machine. Then add your approval cycle.

#### The cost of starting late

We have been invited into projects after the customer already picked four vendors. At that point, all you can do is send a bid. The specs are written, the architecture is set, and you are competing on price alone.

The teams that get the best machines start talking early. When we help shape the machine concept with the customer, they often skip the three-bid process and move faster.

#### How to shorten the timeline

- **Start before you are sure.** You do not need a full spec, CAD files, or throughput data to start a conversation. A site visit and a look at the parts is enough.
- **Bring automation people in early.** The best time is before the product design is validated. (See: *When Should Automation Engineers Get Involved in Medical Device R&D?*)
- **Check your incoming parts now.** Tighter, more consistent parts mean less debugging later.
- **Get leadership on board.** Andy once quoted a machine that had clear labor savings, but upper management never backed it. The quote sat for 21 years. It moved forward only when a new CEO, an engineer, made automation a priority.
- **Think modular.** A machine built to run several part numbers can cover more of your demand with one project. (See: *Can One Automated Machine Handle Multiple Part Numbers?*)

#### Frequently asked questions

**How long does it take to build a custom automation machine?** Most custom machines are quoted at around 26 weeks. In practice, delivery is often closer to 40 weeks, plus a few weeks of debugging. Plan on about a year from PO to steady production.

**When does automation start paying for itself?** Payback starts when the machine makes good parts, not when you place the order. Most manufacturers target a two-year payback from labor savings after the machine is running.

**What do I need before I contact an automation company?** Less than you think. Larger companies sometimes bring user and functional requirement specs. Most teams start with a site visit and a look at the parts. You do not need CAD files or throughput data to begin.

**Why do automation projects run late?** Custom machines are one-of-a-kind. Programming happens at the end, real parts vary more than expected, and validated medical device designs can't change to make automation easier.

#### Start the conversation now

If automation might be on your list in the next year or two, now is the time to talk. Book a free automation audit. One of our engineers will look at your process, your parts, and your labor, and tell you honestly whether automation makes sense.

[Book a Free Automation Audit](https://www.pezosolutions.com/get-in-touch)

## Share this post

<https://www.facebook.com/sharer/sharer.php?u=https%3A%2F%2Fwww.pezosolutions.com%2Fthe-cleanroom-ledger%2Fhow-long-does-custom-automation-take><https://twitter.com/intent/tweet?url=https%3A%2F%2Fwww.pezosolutions.com%2Fthe-cleanroom-ledger%2Fhow-long-does-custom-automation-take><https://www.linkedin.com/shareArticle?mini=true&url=https%3A%2F%2Fwww.pezosolutions.com%2Fthe-cleanroom-ledger%2Fhow-long-does-custom-automation-take><https://pinterest.com/pin/create/button/?url=https%3A%2F%2Fwww.pezosolutions.com%2Fthe-cleanroom-ledger%2Fhow-long-does-custom-automation-take>[mailto:https%3A%2F%2Fwww.pezosolutions.com%2Fthe-cleanroom-ledger%2Fhow-long-does-custom-automation-take](mailto:https%3A%2F%2Fwww.pezosolutions.com%2Fthe-cleanroom-ledger%2Fhow-long-does-custom-automation-take)

## Keep reading

### [![An engineer and a plant manager review a compact automation cell on a medical device production floor while an operator works nearby.](https://www.pezosolutions.com/hs-fs/hubfs/operators_assembling_medical_d_85356_Nano_Banana_2.png?width=1000&height=558&name=operators_assembling_medical_d_85356_Nano_Banana_2.png) Manufacturing Manufacturing Automation When Does It Make Financial Sense to Automate a Manufacturing Process?](https://www.pezosolutions.com/the-cleanroom-ledger/when-does-it-make-financial-sense-to-automate)

### [![Operator working comfortably at a modular workstation with a compact semi-automated fixture on a clean medical device assembly line.](https://www.pezosolutions.com/hs-fs/hubfs/operators_assembling_medical_d_17754_Nano_Banana_2.png?width=1000&height=558&name=operators_assembling_medical_d_17754_Nano_Banana_2.png) Ergonomics Less Scrap Clear Labor Payback 3 Reasons to Automate Your Manufacturing Process](https://www.pezosolutions.com/the-cleanroom-ledger/3-reasons-to-automate-manufacturing-process)

[![white](https://www.pezosolutions.com/hubfs/white.svg "white")](https://www.pezosolutions.com/)

- [Capabilities](https://www.pezosolutions.com/the-cleanroom-ledger/how-long-does-custom-automation-take#capabilities)
- [Cleanroom Workstations](https://www.pezosolutions.com/elevt-workstations)
- [GS 5T](https://www.pezosolutions.com/gs-5t-bench-top-catheter-overmolding-press)
- [About](https://www.pezosolutions.com/about)
- [Blog](https://www.pezosolutions.com/the-cleanroom-ledger)

<https://www.linkedin.com/company/pezo-solutions>

---

Pezo Solutions, 108 Dundas Rd Building F2, Monticello, Minnesota 55362. (833) 234-7396

 

Privacy Policy · Legal · © 2025 Pezo Solutions. All rights reserved.

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Mark Kiviahde",
    "url" : "https://www.pezosolutions.com/the-cleanroom-ledger/author/mark-kiviahde"
  },
  "dateModified" : "2026-11-18T22:38:58.603Z",
  "datePublished" : "2026-11-18T22:38:50.000Z",
  "headline" : "How Long Does Custom Automation Take? Plan for a Year",
  "image" : [ "https://www.pezosolutions.com/hubfs/image-32cf2c86-a1b3-4472-94ed-c70747324b7e.png" ],
  "mainEntityOfPage" : {
    "@id" : "https://www.pezosolutions.com/the-cleanroom-ledger/how-long-does-custom-automation-take",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "url" : "https://www.pezosolutions.com/hubfs/accent1.png"
    },
    "name" : "Pezo Solutions"
  }
}
```

```json
{
  "@context" : "https://schema.org",
  "@type" : "FAQPage",
  "mainEntity" : [ {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Most custom machines are quoted at around 26 weeks. In practice, delivery is often closer to 40 weeks, plus a few weeks of debugging. Plan on about a year from PO to steady production."
    },
    "name" : "How long does it take to build a custom automation machine?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Payback starts when the machine makes good parts, not when you place the order. Most manufacturers target a two-year payback from labor savings after the machine is running."
    },
    "name" : "When does automation start paying for itself?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Less than you think. Larger companies sometimes bring user and functional requirement specs. Most teams start with a site visit and a look at the parts. You do not need CAD files or throughput data to begin."
    },
    "name" : "What do I need before I contact an automation company?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Custom machines are one-of-a-kind. Programming happens at the end, real parts vary more than expected, and validated medical device designs can't change to make automation easier."
    },
    "name" : "Why do automation projects run late?"
  } ]
}
```